Boeing Access Rd over BNRR Bridge Rehabilitation
Project Overview
Rehabilitate the existing bridge that will be 110′ wide curb to curb with sidewalks on both sides.
Timeline
Estimated completion February 2019.
Contact Information
For specific questions, contact Steve Carstens, Program Manager, at (206) 431-2446 or email at steve.carstens@tukwilawa.gov
Project Status Update
Contractor continues to work on the southern two lanes to prepare the area to be widened. The work below deck continues to proceed on schedule. The crews are carbon-fiber wrapping the girders, installing column jackets, and finalizing the western support abutment and pier extensions.
Construction Photos