Project Overview

Rehabilitate the existing bridge that will be 110′ wide curb to curb with sidewalks on both sides.

 

Timeline

Estimated completion February 2019.

 

Contact Information

For specific questions, contact Steve Carstens, Program Manager, at (206) 431-2446 or email at steve.carstens@tukwilawa.gov

 

Project Status Update

Contractor continues to work on the southern two lanes to  prepare the area to be widened. The work below deck  continues to proceed on schedule. The crews are carbon-fiber wrapping the girders, installing column jackets, and  finalizing the western support abutment and pier extensions.

 