Green River Trail Improvements

Project Overview

Construction of approximately 700 linear feet of concrete multi-use trail improvements within the right-of-way of the Green River Trail, including but not limited to clearing and tree removal, excavation and embankment, concrete paving, landscaping and irrigation, decorative concrete treatments, and lighting and camera systems.

 

Future Inconveniences

Last updated: June 10, 2024

  • With 160 cubic yards of concrete done, the majority of trail has been finished. Next is the decorative elements at the Christensen Road end. After this will be landscaping.
  • Project is on schedule and looking at a rough substantial completion date of August 2024 to open the trail up to public use. Due to long lead times, trail illumination poles will be arriving and installed around February of 2025
  • Trail will be closed during entire construction project. Detour signage will be maintained to help with this inconvenience.

 