Major Maintenance on 3 Bridges
Project Overview
Seismic Retrofit, deck and joint repair, and bridge painting on the Frank Zepp Bridge (S 180th St), Grady Way Bridge and the Beacon Avenue South Bridge. The proposed work will preserve the City owned infrastructure and extend the service lives of the bridges. The three bridges were identified as good candidates for federal funding under the Local Agency Bridge Program administered by WSDOT.
Timeline
Construction began in July 2017 and was completed in February 2019.
Contact Information
For specific questions, contact Steve Carstens at 206-431-2446 or email at steve.carstens@tukwilawa.gov
Project Status Update as of 2/14/19
Razz Construction was issued a Notice to Proceed on 7/12/17 for $2,688,958.00.
Grady Way Bridge:
Work on this structure is substantially complete. The Contractor is anticipating to complete the remaining punchlist item by the end of June.
Frank Zepp Bridge (S 180th)
Work on this structure is substantially complete. The Contractor is anticipating to complete the remaining punchlist item by the end of June
Beacon Avenue Bridge
Work on this structure is substantially complete. The Contractor is anticipating to complete the remaining punchlist items by the end of June. Contractor will be returning on 6/18/18 to install some remaining pedestrian safety items on the structure.